An Execution Path is the actual progression through Sequence Steps during Test Execution.

A Test Sequence defines the permitted progression through its Sequence Steps. An Execution Path identifies the progression that actually occurs during a particular Test Run.

An Execution Path can identify:

  • Its initial Sequence Steps
  • Each performed Sequence Step
  • The order in which Sequence Steps occurred
  • Concurrent Sequence Steps
  • Repeated Sequence Steps
  • Skipped Sequence Steps
  • Conditional branches taken
  • Conditional branches not taken
  • Error-handling branches taken
  • The Test Argument Values supplied to each occurrence
  • The Starting Conditions applicable to each occurrence
  • The Timing Conditions applicable to each occurrence
  • The start and completion time of each occurrence
  • The event or condition that caused each progression
  • The applicable Test Result for each occurrence
  • The applicable Verdict for each occurrence
  • The point and cause of termination

An Execution Path can contain:

  • Sequential progression
  • Parallel progression
  • Conditional progression
  • Iterative progression
  • Event-driven progression
  • Error-handling progression
  • A combination of progression types

actual progression through Sequence Steps during Test Execution

Adapted from:

OMG TestIF defines TestSequence as a directed progression of SequenceSteps and permits progression to depend on the applicable Sequence Step relationships and conditions.

OMG TestIF discusses test paths but does not establish Execution Path as a separate TestIF model element. This definition introduces Execution Path to identify the Test Sequence progression that actually occurred during a particular Test Run.

Use the singular glossary term Execution Path. Link plural usage to the same controlling page:

[[dido:99_annexes:annex-b-terms-and-definitions:e:execution_path|Execution Paths]]

An Execution Path differs from a Test Sequence:

  • A Test Sequence defines permitted progression
  • An Execution Path identifies the progression that actually occurred

A Test Sequence can permit multiple Execution Paths.

An Execution Path differs from a Sequence Step:

  • A Sequence Step identifies one position and occurrence within a Test Sequence
  • An Execution Path identifies the actual progression through the performed Sequence Steps

An Execution Path differs from a Test Run:

  • An Execution Path identifies the actual progression
  • A Test Run records the Execution Path, execution context, Test Results, Evidence, and related information for a particular occurrence of Test Execution

An Execution Path differs from a Test Result:

  • An Execution Path identifies what progression occurred
  • A Test Result records an outcome associated with a Sequenced Test Object or Sequence Step

A repeated Test Run does not necessarily follow the same Execution Path. Differences can result from:

  • Different Test Argument Values
  • Different Starting Conditions
  • Different Test Results
  • Different Verdicts
  • Different Timing Conditions
  • Timeouts
  • Errors
  • Concurrent behavior
  • External events
  • Nondeterministic behavior

The applicable Acceptance Criteria determine whether reproducible Test Execution requires:

  • The same Execution Path
  • An equivalent Execution Path
  • Any permitted Execution Path
  • A particular set of required Sequence Steps
  • Exclusion of prohibited Execution Paths

Parallel progression does not always establish a single total ordering. An Execution Path can preserve a partial ordering that identifies concurrency and the required temporal relationships among Sequence Steps.

An Execution Path should preserve enough information to reconstruct:

  • Which Sequence Steps occurred
  • Which Sequence Steps did not occur
  • The order or partial order of occurrence
  • The Test Argument Values used
  • The conditions that controlled progression
  • The Test Results produced
  • The reason Test Execution completed or terminated

A Test Sequence permits the following progression:

  • Sequence Step SS-01 establishes a Node Set
  • Sequence Step SS-02 submits a transaction
  • Sequence Steps SS-03A, SS-03B, and SS-03C observe three Nodes concurrently
  • Sequence Step SS-04 evaluates the Test Results when all three Nodes respond
  • Sequence Step SS-05 handles a timeout when one or more Nodes fail to respond

During one Test Run, all three Nodes respond. The Execution Path is:

  • SS-01
  • SS-02
  • Concurrent occurrence of SS-03A, SS-03B, and SS-03C
  • SS-04

During a repeated Test Run, Node C fails to respond. The Execution Path is:

  • SS-01
  • SS-02
  • Concurrent occurrence of SS-03A, SS-03B, and SS-03C
  • SS-05

The two Test Runs use the same Test Sequence but follow different Execution Paths. The Acceptance Criteria determine whether both Execution Paths satisfy the applicable Reproducibility requirement.


© 2026 Dido Solutions, Inc. and Jackrabbit Consulting, Inc.

  • dido/99_annexes/annex-b-terms-and-definitions/e/execution_path.txt
  • Last modified: 2026/08/05 02:04
  • by nick_dido