MO-002 — Reduced Platform Deployment Timelines

Crucible SHALL reduce platform deployment timelines from months to days or hours through automation.[C2]

The Original Requirement preserves the approved mission objective but does not express independently testable normative statements.

The following Specification Discipline and Authoring findings apply:

  • Reduce requires comparison with an identified and approved baseline, but the Original Requirement does not identify the baseline process, duration, scope, inputs, or measurement method
  • Platform deployment timelines does not identify the starting event, completion event, measured activities, or measurement boundaries
  • From months does not identify a specific baseline duration or a bounded range
  • To days or hours provides alternative and unbounded target ranges rather than a single applicable Acceptance Criterion
  • Through automation prescribes an implementation approach rather than stating only the required outcome
  • The Original Requirement does not identify the applicable Platform Deployment
  • The Original Requirement does not identify which Platform Deployment activities contribute to the measured Deployment Duration
  • The Original Requirement does not identify how failed, incomplete, interrupted, or repeated deployments affect the measured result
  • The Original Requirement combines an absolute duration objective, a relative duration-reduction objective, and an implementation approach within one compound normative statement
  • The absolute duration objective and relative duration-reduction objective may pass or fail independently
  • The Original Requirement does not provide independently identifiable statements for verification and traceability

The Original Requirement therefore requires decomposition into independently identifiable normative requirements.

The decomposition preserves MO-002 as the stable parent requirement identifier. Each replacement requirement receives a lettered identifier and a separate requirement page. The source page currently combines the maximum permitted duration and improvement over an approved Deployment Baseline in one normalized Statement, so those outcomes also require separation. :contentReference[oaicite:0]{index=0}

The Original Requirement is replaced by the following independently identifiable normative requirements: